# §63.11150. What General Provisions apply to this subpart?

- (a) If you own or operate a new or existing affected source, you must comply with the requirements of the General Provisions ([40 CFR part 63](/cfr/40/part63.md), [subpart A](/cfr/40/subpartA.md)) as specified in Table 1 to this subpart.
- (b) If you own or operate an existing affected source subject to [§ 63.11147](/cfr/40/63.11147.md), your notification of compliance status required by [§ 63.9(h)](/cfr/40/63.9.md?p=h) must include the information specified in [paragraphs (b)(1) through (4)](#b-1..b-4) of this section.
  - (1) If you certify initial compliance with the PM emissions limit in [§ 63.11147(a)(1)](/cfr/40/63.11147.md?p=a-1) based on monitoring data from the previous month, your notification of compliance status must include this certification of compliance, signed by a responsible official: “This facility complies with the PM emissions limit in [§ 63.11147(a)(1)](/cfr/40/63.11147.md?p=a-1) based on monitoring data that were collected during the previous month.”
  - (2) If you conduct a new performance test to demonstrate initial compliance with the PM emissions limit in [§ 63.11147(a)(1)](/cfr/40/63.11147.md?p=a-1), your notification of compliance status must include the results of the performance test, including required monitoring data.
  - (3) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11147(a)(2)](/cfr/40/63.11147.md?p=a-2): “This facility complies with the requirement to capture gases from transfer of molten materials from smelting vessels and converting vessels and convey them to a control device in accordance with [§ 63.11147(a)(2)](/cfr/40/63.11147.md?p=a-2).”
  - (4) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11147(a)(3)](/cfr/40/63.11147.md?p=a-3): “This facility complies with the requirement to capture gases from operations in the anode refining department and convey them to a PM control device in accordance with [§ 63.11147(a)(3)](/cfr/40/63.11147.md?p=a-3).”
- (c) If you own or operate an existing affected source subject to [§ 63.11148](/cfr/40/63.11148.md), your notification of compliance status required by [§ 63.9(h)](/cfr/40/63.9.md?p=h) must include the information specified in [paragraphs (c)(1) through (5)](#c-1..c-5) of this section.
  - (1) If you certify initial compliance with the PM emissions limit in § [63.11148(a)(1)](/cfr/40/63.11148.md?p=a-1), [(a)(3)(ii)](/cfr/40/63.11148.md?p=a-3-ii), and [(a)(4)(iv)](/cfr/40/63.11148.md?p=a-4-iv) based on the results of a previous performance test conducted within the past 12 months before your compliance date, your notification of compliance status must include this certification of compliance, signed by a responsible official: “This facility complies with the PM emissions limit in [§ 63.11148(a)(1)](/cfr/40/63.11148.md?p=a-1) based on the results of a previous performance test.”
  - (2) If you conduct a new performance test to demonstrate initial compliance with the PM emissions limits in § [63.11148(a)(1)](/cfr/40/63.11148.md?p=a-1), [(a)(3)(ii)](/cfr/40/63.11148.md?p=a-3-ii), and [(a)(4)(iv)](/cfr/40/63.11148.md?p=a-4-iv), your notification of compliance status must include the results of the performance test, including required monitoring data.
  - (3) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standards in § [63.11148(a)(2)](/cfr/40/63.11148.md?p=a-2), and [(a)(4)(iii)](/cfr/40/63.11148.md?p=a-4-iii): “This facility complies with the requirement to vent captured process gases to a gas cleaning system controlling PM and to a sulfuric acid plant in accordance with § [63.11148(a)(2)](/cfr/40/63.11148.md?p=a-2) and [(a)(4)(iii)](/cfr/40/63.11148.md?p=a-4-iii).”
  - (4) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11148(a)(3)(i)](/cfr/40/63.11148.md?p=a-3-i): “This facility complies with the requirement to operate capture systems to collect gases and fumes released when copper matte or slag is tapped from the smelting vessel in accordance with [§ 63.11148(a)(3)(i)](/cfr/40/63.11148.md?p=a-3-i).”
  - (5) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11148(a)(4)](/cfr/40/63.11148.md?p=a-4): “This facility complies with the requirement to operate capture systems to collect gases and fumes released during batch copper converter operations in accordance with [§ 63.11148(a)(4)](/cfr/40/63.11148.md?p=a-4).”
- (d) If you own or operate a new affected source, your notification of compliance status required by [§ 63.9(h)](/cfr/40/63.9.md?p=h) must include the information in [paragraphs (d)(1) through (3)](#d-1..d-3) of this section.
  - (1) Your notification of compliance status must include the results of the initial performance test and monitoring data collected during the test that demonstrate compliance with the emissions limit in [§ 63.11149(a)(1)](/cfr/40/63.11149.md?p=a-1).
  - (2) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11149(a)(2)](/cfr/40/63.11149.md?p=a-2): “This facility complies with the requirement to capture gases from transfer of molten materials from smelting vessels and converting vessels and convey them to a PM control device in accordance with [§ 63.11149(a)(2)](/cfr/40/63.11149.md?p=a-2).”
  - (3) Your notification of compliance status must include this certification of compliance, signed by a responsible official, for the work practice standard in [§ 63.11149(a)(3)](/cfr/40/63.11149.md?p=a-3): “This facility complies with the requirement to capture gases from each vessel used to refine blister copper, remelt anode copper, or remelt anode scrap, and convey them to a PM control device in accordance with [§ 63.11149(a)(3)](/cfr/40/63.11149.md?p=a-3).”

## Notes

### Amendments

[72 FR 2944, Jan. 23, 2007, as amended at 72 FR 36367, July 3, 2007]

### Source

Source: 72 FR 2944, Jan. 23, 2007, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.

### Amendments

[72 FR 2944, Jan. 23, 2007, as amended at 72 FR 36367, July 3, 2007]