# §63.11118. Requirements for facilities with monthly throughput of 100,000 gallons of gasoline or more.

- (a) You must comply with the requirements in §§ [63.11116(a)](/cfr/40/63.11116.md?p=a) and [63.11117(b)](/cfr/40/63.11117.md?p=b).
- (b) Except as provided in [paragraph (c)](#c) of this section, you must meet the requirements in either [paragraph (b)(1)](#b-1) or [paragraph (b)(2)](#b-2) of this section.
  - (1) Each management practice in Table 1 to this subpart that applies to your GDF.
  - (2) If, prior to January 10, 2008, you satisfy the requirements in both paragraphs [(b)(2)(i)](#b-2-i) and [(ii)](#b-2-ii) of this section, you will be deemed in compliance with this subsection.
    - (i) You operate a vapor balance system at your GDF that meets the requirements of either [paragraph (b)(2)(i)(A)](#b-2-i-A) or [paragraph (b)(2)(i)(B)](#b-2-i-B) of this section.
      - (A) **Achieves emissions reduction of at least 90 percent.**
      - (B) **Operates using management practices at least as stringent as those in Table 1 to this subpart.**
    - (ii) Your gasoline dispensing facility is in compliance with an enforceable State, local, or tribal rule or permit that contains requirements of either [paragraph (b)(2)(i)(A)](#b-2-i-A) or [paragraph (b)(2)(i)(B)](#b-2-i-B) of this section.
- (c) The emission sources listed in [paragraphs (c)(1) through (3)](#c-1..c-3) of this section are not required to comply with the control requirements in [paragraph (b)](#b) of this section, but must comply with the requirements in [§ 63.11117](/cfr/40/63.11117.md).
  - (1) Gasoline storage tanks with a capacity of less than 250 gallons that are constructed after January 10, 2008.
  - (2) Gasoline storage tanks with a capacity of less than 2,000 gallons that were constructed before January 10, 2008.
  - (3) **Gasoline storage tanks equipped with floating roofs, or the equivalent.**
- (d) Cargo tanks unloading at GDF must comply with the management practices in Table 2 to this subpart.
- (e) You must comply with the applicable testing requirements contained in [§ 63.11120](/cfr/40/63.11120.md).
- (f) You must submit the applicable notifications as required under [§ 63.11124](/cfr/40/63.11124.md).
- (g) You must keep records and submit reports as specified in §§ [63.11125](/cfr/40/63.11125.md) and [63.11126](/cfr/40/63.11126.md).
- (h) You must comply with the requirements of this subpart by the applicable dates contained in [§ 63.11113](/cfr/40/63.11113.md).

## Notes

### Amendments

[73 FR 1945, Jan. 10, 2008, as amended at 73 FR 12276, Mar. 7, 2008]

### Source

Source: 73 FR 1945, Jan. 10, 2008, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.

### Amendments

[73 FR 1945, Jan. 10, 2008, as amended at 73 FR 12276, Mar. 7, 2008]