# §62.14560. How do I comply with the increment of progress for submittal of a control plan?


For your control plan increment of progress, you must satisfy the two requirements specified in paragraphs [(a)](#a) and [(b)](#b) of this section.

- (a) Submit the final control plan that includes the six items described in [paragraphs (a)(1) through (6)](#a-1..a-6) of this section.
  - (1) A description of the devices for air pollution control and process changes that you will use to comply with the emission limitations and other requirements of this subpart.
  - (2) **The type(s) of waste to be burned.**
  - (3) **The maximum design waste burning capacity.**
  - (4) **The anticipated maximum charge rate.**
  - (5) If applicable, the petition for site-specific operating limits under [§ 62.14640](/cfr/40/62.14640.md).
  - (6) A schedule that includes the date by which you will award the contracts to procure emission control equipment or related materials, initiate on-site construction, initiate on-site installation of emission control equipment, and/or incorporate process changes, and the date by which you will initiate on-site construction.
- (b) **Maintain an on-site copy of the final control plan.**

## Notes

### Source

Source: 68 FR 57539, Oct. 3, 2003, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 43 FR 51393, Nov. 3, 1978, unless otherwise noted.