# §60.692-7. Standards: Delay of compliance.

- (a) Delay of compliance of modified individual drain systems with ancillary downstream treatment components will be allowed if compliance with the provisions of this subpart cannot be achieved without a refinery or process unit shutdown.
- (b) Installation of equipment necessary to comply with the provisions of this subpart shall occur no later than the next scheduled refinery or process unit shutdown.

## Notes

### Source

Source: 53 FR 47623, Nov. 23, 1988, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.