---
kind: "section"
citation: "40 C.F.R. § 60.6355"
title: "40"
number: "60.6355"
heading: "How do I comply with the increment of progress for submittal of a control plan?"
url: "https://uscodex.org/cfr/40/60.6355"
---

# §60.6355. How do I comply with the increment of progress for submittal of a control plan?


For your control plan increment of progress, you must complete two items:

- (a) Submit the final control plan, including a description of the devices for air pollution control and process changes that you will use to comply with the emission limits and other requirements of this subpart.
- (b) You must maintain an onsite copy of the final control plan.

## Notes

### Source

Source: 91 FR 11860, Mar. 10, 2026, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.
