# §60.6330. What are my requirements for meeting increments of progress and achieving final compliance?


If you plan to achieve compliance more than 1 year but less than 3 years following the effective date of state plan approval and a permit modification is not required, or more than 1 year but less than 3 years following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:

- (a) **Submit a final control plan.**
- (b) **Submit a notification of retrofit contract award.**
- (c) **Initiate onsite construction.**
- (d) **Complete onsite construction.**
- (e) **Achieve final compliance.**

## Notes

### Source

Source: 91 FR 11860, Mar. 10, 2026, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.