# §60.5715b. What is the review and approval process for my State plan?

- (a) The EPA will determine the completeness of your State plan submission according to [§ 60.27a(g)](/cfr/40/60.27a.md?p=g). The timeline for completeness determinations is provided in [§ 60.27a(g)(1)](/cfr/40/60.27a.md?p=g-1).
- (b) The EPA will act on your State plan submission according to [§ 60.27a](/cfr/40/60.27a.md). The Administrator will have 12 months after the date the final State plan or State plan revision (as allowed under [§ 60.5790b](/cfr/40/60.5790b.md)) is found to be complete to fully approve, partially approve, conditionally approve, partially disapprove, and/or fully disapprove such State plan or revision or each portion thereof.

## Notes

### Source

Source: 89 FR 40047, May 9, 2024, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.