# §60.5240. Am I required to apply for and obtain a Title V operating permit for my existing SSI unit?


Yes, if you are subject to an applicable EPA-approved and effective CAA [section 111(d)](/cfr/40/111.md?p=d)/129 state or tribal plan or an applicable and effective Federal plan, you are required to apply for and obtain a Title V operating permit for your existing SSI unit unless you meet the relevant requirements for an exemption specified in [§ 60.5065](/cfr/40/60.5065.md).


## Notes

### Source

Source: 76 FR 15404, Mar. 21, 2011, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.