# §75.250. Maximum project period.


The Secretary may approve a project period of up to 60 months to perform the substantive work of a grant unless an applicable statute provides otherwise.


## Notes

### Amendments

[89 FR 70328, Aug. 29, 2024]

### Authority

Authority: 20 U.S.C. 1221e-3 and 3474, unless otherwise noted. Section 75.263 also issued under 2 CFR 200.308(e)(1). Section 75.617 also issued under 31 U.S.C. 3504, 3505. Section 75.740 also issued under 20 U.S.C. 1232g and 1232h.