# §326.1. Purpose.


This part prescribes enforcement policies ([§ 326.2](/cfr/33/326.2.md)) and procedures applicable to activities performed without required Department of the Army permits ([§ 326.3](/cfr/33/326.3.md)) and to activities not in compliance with the terms and conditions of issued Department of the Army permits ([§ 326.4](/cfr/33/326.4.md)). Procedures for initiating legal actions are prescribed in [§ 326.5](/cfr/33/326.5.md). Nothing contained in this part shall establish a non-discretionary duty on the part of district engineers nor shall deviation from these procedures give rise to a private right of action against a district engineer.


# §326.2. Policy.


Enforcement, as part of the overall regulatory program of the Corps, is based on a policy of regulating the waters of the United States by discouraging activities that have not been properly authorized and by requiring corrective measures, where appropriate, to ensure those waters are not misused and to maintain the integrity of the program. There are several methods discussed in the remainder of this part which can be used either singly or in combination to implement this policy, while making the most effective use of the enforcement resources available. As EPA has independent enforcement authority under the Clean Water Act for unauthorized discharges, the district engineer should normally coordinate with EPA to determine the most effective and efficient manner by which resolution of a [section 404](/cfr/33/404.md) violation can be achieved.


# §326.3. Unauthorized activities.

- (a) **Surveillance.** To detect unauthorized activities requiring permits, district engineers should make the best use of all available resources. Corps employees; members of the public; and representatives of state, local, and other Federal agencies should be encouraged to report suspected violations. Additionally, district engineers should consider developing joint surveillance procedures with Federal, state, or local agencies having similar regulatory responsibilities, special expertise, or interest.
- (b) **Initial investigation.** District engineers should take steps to investigate suspected violations in a timely manner. The scheduling of investigations will reflect the nature and location of the suspected violations, the anticipated impacts, and the most effective use of inspection resources available to the district engineer. These investigations should confirm whether a violation exists, and if so, will identify the extent of the violation and the parties responsible.
- (c) **Formal notifications to parties responsible for violations.** Once the district engineer has determined that a violation exists, he should take appropriate steps to notify the responsible parties.
  - (1) If the violation involves a project that is not complete, the district engineer's notification should be in the form of a cease and desist order prohibiting any further work pending resolution of the violation in accordance with the procedures contained in this part. See [paragraph (c)(4)](#c-4) of this section for exception to this procedure.
  - (2) If the violation involves a completed project, a cease and desist order should not be necessary. However, the district engineer should still notify the responsible parties of the violation.
  - (3) All notifications, pursuant to [paragraphs (c)](#c) (1) and (2) of this section, should identify the relevant statutory authorities, indicate potential enforcement consequences, and direct the responsible parties to submit any additional information that the district engineer may need at that time to determine what course of action he should pursue in resolving the violation; further information may be requested, as needed, in the future.
  - (4) In situations which would, if a violation were not involved, qualify for emergency procedures pursuant to [33 CFR part 325.2(e)(4)](/cfr/33/325.2.md?p=e-4), the district engineer may decide it would not be appropriate to direct that the unauthorized work be stopped. Therefore, in such situations, the district engineer may, at his discretion, allow the work to continue, subject to appropriate limitations and conditions as he may prescribe, while the violation is being resolved in accordance with the procedures contained in this part.
  - (5) When an unauthorized activity requiring a permit has been undertaken by American Indians (including Alaskan natives, Eskimos, and Aleuts, but not including Native Hawaiians) on reservation lands or in pursuit of specific treaty rights, the district engineer should use appropriate means to coordinate proposed directives and orders with the Assistant Chief Counsel for Indian Affairs (DAEN-CCI).
  - (6) When an unauthorized activity requiring a permit has been undertaken by an official acting on behalf of a foreign government, the district engineer should use appropriate means to coordinate proposed directives and orders with the Office, Chief of Engineers, ATTN: DAEN-CCK.
- (d) **Initial corrective measures.**
  - (1) The district engineer should, in appropriate cases, depending upon the nature of the impacts associated with the unauthorized, completed work, solicit the views of the Environmental Protection Agency; the U.S. Fish and Wildlife Service; the National Marine Fisheries Service, and other Federal, state, and local agencies to facilitate his decision on what initial corrective measures are required. If the district engineer determines as a result of his investigation, coordination, and preliminary evaluation that initial corrective measures are required, he should issue an appropriate order to the parties responsible for the violation. In determining what initial corrective measures are required, the district engineer should consider whether serious jeopardy to life, property, or important public resources (see [33 CFR 320.4](/cfr/33/320.4.md)) may be reasonably anticipated to occur during the period required for the ultimate resolution of the violation. In his order, the district engineer will specify the initial corrective measures required and the time limits for completing this work. In unusual cases where initial corrective measures substantially eliminate all current and future detrimental impacts resulting from the unauthorized work, further enforcement actions should normally be unnecessary. For all other cases, the district engineer's order should normally specify that compliance with the order will not foreclose the Government's options to initiate appropriate legal action or to later require the submission of a permit application.
  - (2) An order requiring initial corrective measures that resolve the violation may also be issued by the district engineer in situations where the acceptance or processing of an after-the-fact permit application is prohibited or considered not appropriate pursuant to [§ 326.3(e)(1)](#e-1) (iii) through (iv) below. However, such orders will be issued only when the district engineer has reached an independent determination that such measures are necessary and appropriate.
  - (3) It will not be necessary to issue a Corps permit in connection with initial corrective measures undertaken at the direction of the district engineer.
- (e) **After-the-fact permit applications.**
  - (1) Following the completion of any required initial corrective measures, the district engineer will accept an after-the-fact permit application unless he determines that one of the exceptions listed in subparagraphs i-iv below is applicable. Applications for after-the-fact permits will be processed in accordance with the applicable procedures in 33 CFR parts [320](/cfr/33/part320.md) through [325](/cfr/33/part325.md). Situations where no permit application will be processed or where the acceptance of a permit application must be deferred are as follows:
    - (i) No permit application will be processed when restoration of the waters of the United States has been completed that eliminates current and future detrimental impacts to the satisfaction of the district engineer.
    - (ii) No permit application will be accepted in connection with a violation where the district engineer determines that legal action is appropriate ([§ 326.5(a)](/cfr/33/326.5.md?p=a)) until such legal action has been completed.
    - (iii) No permit application will be accepted where a Federal, state, or local authorization or certification, required by Federal law, has already been denied.
    - (iv) No permit application will be accepted nor will the processing of an application be continued when the district engineer is aware of enforcement litigation that has been initiated by other Federal, state, or local regulatory agencies, unless he determines that concurrent processing of an after-the-fact permit application is clearly appropriate.
    - (v) No appeal of an approved jurisdictional determination (JD) associated with an unauthorized activity or after-the-fact permit application will be accepted unless and until the applicant has furnished a signed statute of limitations tolling agreement to the district engineer. A separate statute of limitations tolling agreement will be prepared for each unauthorized activity. Any person who appeals an approved JD associated with an unauthorized activity or applies for an after-the-fact permit, where the application is accepted and evaluated by the Corps, thereby agrees that the statute of limitations regarding any violation associated with that application is suspended until one year after the final Corps decision, as defined at [33 CFR 331.10](/cfr/33/331.10.md). Moreover, the recipient of an approved JD associated with an unauthorized activity or an application for an after-the-fact permit must also memorialize that agreement to toll the statute of limitations, by signing an agreement to that effect, in exchange for the Corps acceptance of the after-the-fact permit application, and/or any administrative appeal. Such agreement will state that, in exchange for the Corps acceptance of any after-the-fact permit application and/or any administrative appeal associated with the unauthorized activity, the responsible party agrees that the statute of limitations will be suspended (i.e., tolled) until one year after the final Corps decision on the after-the-fact permit application or, if there is an administrative appeal, one year after the final Corps decision as defined at [33 CFR 331.10](/cfr/33/331.10.md), whichever date is later.
  - (2) Upon completion of his review in accordance with 33 CFR parts [320](/cfr/33/part320.md) through [325](/cfr/33/part325.md), the district engineer will determine if a permit should be issued, with special conditions if appropriate, or denied. In reaching a decision to issue, he must determine that the work involved is not contrary to the public interest, and if [section 404](/cfr/33/404.md) is applicable, that the work also complies with the Environmental Protection Agency's [section 404(b)(1)](/cfr/33/404.md?p=b-1) guidelines. If he determines that a denial is warranted, his notification of denial should prescribe any final corrective actions required. His notification should also establish a reasonable period of time for the applicant to complete such actions unless he determines that further information is required before the corrective measures can be specified. If further information is required, the final corrective measures may be specified at a later date. If an applicant refuses to undertake prescribed corrective actions ordered subsequent to permit denial or refuses to accept a conditioned permit, the district engineer may initiate legal action in accordance with [§ 326.5](/cfr/33/326.5.md).
- (f) **Combining steps.** The procedural steps in this section are in the normal sequence. However, these regulations do not prohibit the streamlining of the enforcement process through the combining of steps.
- (g) **Coordination with EPA.** In all cases where the district engineer is aware that EPA is considering enforcement action, he should coordinate with EPA to attempt to avoid conflict or duplication. Such coordination applies to interim protective measures and after-the-fact permitting, as well as to appropriate legal enforcement actions.

# §326.4. Supervision of authorized activities.

- (a) **Inspections.** District engineers will, at their discretion, take reasonable measures to inspect permitted activities, as required, to ensure that these activities comply with specified terms and conditions. To supplement inspections by their enforcement personnel, district engineers should encourage their other personnel; members of the public; and interested state, local, and other Federal agency representatives to report suspected violations of Corps permits. To facilitate inspections, district engineers will, in appropriate cases, require that copies of ENG Form 4336 be posted conspicuously at the sites of authorized activities and will make available to all interested persons information on the terms and conditions of issued permits. The U.S. Coast Guard will inspect permitted ocean dumping activities pursuant to [section 107(c)](/cfr/33/107.md?p=c) of the Marine Protection, Research and Sanctuaries Act of 1972, as amended.
- (b) **Inspection limitations.** Section 326.4 does not establish a non-discretionary duty to inspect permitted activities for safety, sound engineering practices, or interference with other permitted or unpermitted structures or uses in the area. Further, the regulations implementing the Corps regulatory program do not establish a non-discretionary duty to inspect permitted activities for any other purpose.
- (c) **Inspection expenses.** The expenses incurred in connection with the inspection of permitted activities will normally be paid by the Federal Government unless daily supervision or other unusual expenses are involved. In such unusual cases, the district engineer may condition permits to require permittees to pay inspection expenses pursuant to the authority contained in [section 9701](/cfr/33/9701.md) of Pub L. 97-258 ([33 U.S.C. 9701](/usc/33/9701.md)). The collection and disposition of inspection expense funds obtained from applicants will be administered in accordance with the relevant Corps regulations governing such funds.
- (d) **Non-compliance.** If a district engineer determines that a permittee has violated the terms or conditions of the permit and that the violation is sufficiently serious to require an enforcement action, then he should, unless at his discretion he deems it inappropriate: (1) First contact the permittee;
  - (2) Request corrected plans reflecting actual work, if needed; and
  - (3) **Attempt to resolve the violation.** Resolution of the violation may take the form of the permitted project being voluntarily brought into compliance or of a permit modification ([33 CFR 325.7(b)](/cfr/33/325.7.md?p=b)). If a mutually agreeable solution cannot be reached, a written order requiring compliance should normally be issued and delivered by personal service. Issuance of an order is not, however, a prerequisite to legal action. If an order is issued, it will specify a time period of not more than 30 days for bringing the permitted project into compliance, and a copy will be sent to the appropriate state official pursuant to [section 404(s)(2)](/cfr/33/404.md?p=s-2) of the Clean Water Act. If the permittee fails to comply with the order within the specified period of time, the district engineer may consider using the suspension/revocation procedures in [33 CFR 325.7(c)](/cfr/33/325.7.md?p=c) and/or he may recommend legal action in accordance with [§ 326.5](/cfr/33/326.5.md).

# §326.5. Legal action.

- (a) **General.** For cases the district engineer determines to be appropriate, he will recommend criminal or civil actions to obtain penalties for violations, compliance with the orders and directives he has issued pursuant to §§ [326.3](/cfr/33/326.3.md) and [326.4](/cfr/33/326.4.md), or other relief as appropriate. Appropriate cases for criminal or civil action include, but are not limited to, violations which, in the district engineer's opinion, are willful, repeated, flagrant, or of substantial impact.
- (b) **Preparation of case.** If the district engineer determines that legal action is appropriate, he will prepare a litigation report or such other documentation that he and the local U.S. Attorney have mutually agreed to, which contains an analysis of the information obtained during his investigation of the violation or during the processing of a permit application and a recommendation of appropriate legal action. The litigation report or alternative documentation will also recommend what, if any, restoration or mitigative measures are required and will provide the rationale for any such recommendation.
- (c) **Referral to the local U.S. Attorney.** Except as provided in [paragraph (d)](#d) of this section, district engineers are authorized to refer cases directly to the U.S. Attorney. Because of the unique legal system in the Trust Territories, all cases over which the Department of Justice has no authority will be referred to the Attorney General for the trust Territories. Information copies of all letters of referral shall be forwarded to the appropriate division counsel, the Office, Chief of Engineers, ATTN: DAEN-CCK, the Office of the Assistant Secretary of the Army (Civil Works), and the Chief of the Environmental Defense Section, Lands and Natural Resources Division, U.S. Department of Justice.
- (d) **Referral to the Office, Chief of Engineers.** District engineers will forward litigation reports with recommendations through division offices to the Office, Chief of Engineers, ATTN: DAEN-CCK, for all cases that qualify under the following criteria:
  - (1) Significant precedential or controversial questions of law or fact;
  - (2) Requests for elevation to the Washington level by the Department of Justice;
  - (3) Violations of [section 9](/cfr/33/9.md) of the Rivers and Harbors Act of 1899;
  - (4) Violations of [section 103](/cfr/33/103.md) the Marine Protection, Research and Sanctuaries Act of 1972;
  - (5) All cases involving violations by American Indians (original of litigation report to DAEN-CCI with copy to DAEN-CCK) on reservation lands or in pursuit of specific treaty rights;
  - (6) All cases involving violations by officials acting on behalf of foreign governments; and
  - (7) **Cases requiring action pursuant to paragraph (e) of this section.**
- (e) **Legal option not available.** In cases where the local U.S. Attorney declines to take legal action, it would be appropriate for the district engineer to close the enforcement case record unless he believes that the case warrants special attention. In that situation, he is encouraged to forward a litigation report to the Office, Chief of Engineers, ATTN: DAEN-CCK, for direct coordination through the Office of the Assistant Secretary of the Army (Civil Works) with the Department of Justice. Further, the case record should not be closed if the district engineer anticipates that further administrative enforcement actions, taken in accordance with the procedures prescribed in this part, will identify remedial measures which, if not complied with by the parties responsible for the violation, will result in appropriate legal action at a later date.