# §157.148. COW system: Evidence for inspections.

- (a) Before the inspections under [§ 157.140](/cfr/33/157.140.md) are conducted by the Coast Guard, the owner or operator of a foreign tank vessel that is to be inspected must submit to the Coast Guard inspector evidence that the COW system has been installed in accordance with the plans accepted under [§ 157.106](/cfr/33/157.106.md).
- (b) Before the inspections under [§ 157.140](/cfr/33/157.140.md) are conducted by the Coast Guard, the owner or operator of a tank vessel that is to be inspected must submit to the Coast Guard inspector evidence that the COW piping system has passed a test of 1 1/2 times the design working pressure.

## Notes

### Source

Source: CGD 77-058b, 45 FR 43709, June 30, 1980, unless otherwise noted.

### Authority

Authority: 33 U.S.C. 1903; 46 U.S.C. 3703, 3703a (note); Department of Homeland Security Delegation No. 0170.1. Subparts G, H, and I are also issued under section 4115(b), Pub. L. 101-380, 104 Stat. 520; Pub. L. 104-55, 109 Stat. 546.

### Source

Source: CGD 74-32, 40 FR 48283, Oct. 14, 1975, unless otherwise noted.