# §585.614. When may I begin conducting activities under my approved SAP?

- (a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.
- (b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in [§ 585.613(a)(1)](/cfr/30/585.613.md?p=a-1), you must comply with the requirements of [30 CFR part 285](/cfr/30/part285.md), [subpart G](/cfr/30/subpartG.md), and also submit your Safety Management System description required by [30 CFR 285.810](/cfr/30/285.810.md) before construction may begin.