# §285.903. What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?


You must comply with the decommissioning requirements in your BOEM-issued lease. If you fail to comply with the decommissioning requirements of your lease then:

- (a) BOEM may call for the forfeiture of your bond or other financial assurance;
- (b) You remain liable for removal or disposal costs and responsible for accidents or damages that might result from such failure; and
- (c) BSEE may take enforcement action under [§ 285.400](/cfr/30/285.400.md).