# §285.822. What must I do when BSEE conducts an inspection?

- (a) **When BSEE conducts an inspection, you must—**
  - (1) Provide access to all facilities on your lease (including your project easement) or grant and any vessels engaged in activities authorized under this part; and
  - (2) **Make the following available for BSEE to inspect—**
    - (i) The area covered under a lease, ROW grant, or RUE grant;
    - (ii) All improvements, structures, and fixtures on these areas; and
    - (iii) All records of design, construction, operation, maintenance, repairs, or investigations on or related to the area.
- (b) You must retain the records referenced in [paragraph (a)(2)(iii)](#a-2-iii) of this section until BOEM releases your financial assurance under 30 CFR585.534 and provide them to BSEE upon request within the time period specified by BSEE.
- (c) You must demonstrate to the inspector how you are in compliance with your safety management system.

## Notes

### Amendments

[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42721, May 15, 2024]

### Authority

Authority: 43 U.S.C. 1331 et seq.

### Source

Source: 88 FR 6413, Jan. 31, 2023, unless otherwise noted.

### Amendments

[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42721, May 15, 2024]