# §285.816. What must I do if environmental or other conditions adversely affect a cable, pipeline, or facility?


If environmental or other conditions adversely affect a cable, pipeline, or facility so as to endanger the safety or the environment, you must:

- (a) **Submit a plan of corrective action to BSEE within 30 days of the discovery of the adverse effect.**
- (b) **Take remedial action as described in your corrective action plan.**
- (c) **Submit to the BSEE a report of the remedial action taken within 30 days after completion.**

## Notes

### Authority

Authority: 43 U.S.C. 1331 et seq.

### Source

Source: 88 FR 6413, Jan. 31, 2023, unless otherwise noted.