heading: "When may I begin conducting activities under my approved SAP?"
url: "https://uscodex.org/cfr/30/285.614"
---

# §285.614. When may I begin conducting activities under my approved SAP?

- (a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.
- (b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in [30 CFR 585.613(a)(1)](/cfr/30/585.613.md?p=a-1), you must comply with the requirements of [subpart G](/cfr/30/subpartG.md) of this part and submit the Safety Management System (SMS) description required by [§ 285.810](/cfr/30/285.810.md) before construction may begin.

## Notes

### Amendments

[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42715, May 15, 2024]

### Authority

Authority: 43 U.S.C. 1331 et seq.

### Source

Source: 88 FR 6413, Jan. 31, 2023, unless otherwise noted.

### Amendments

[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42715, May 15, 2024]