# §250.918. What are the CVA's primary duties during the installation phase?

- (a) The CVA must use good engineering judgment and practice in conducting an independent assessment of the installation activities.
- (b) **Primary duties of the CVA during the installation phase include the following—**
- (c) The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the installation phase in accordance with the approved schedule required by [§ 250.911(d)](/cfr/30/250.911.md?p=d). In each interim and final report the CVA must:
  - (1) Give details of how, by whom, and when the independent monitoring activities were conducted;
  - (2) Describe the CVA's activities during the verification process;
  - (3) Summarize the CVA's findings;
  - (4) Confirm or deny compliance with the approved installation plan;
  - (5) In the final report, make a recommendation to accept or reject the installation unless such a recommendation has been previously made in an interim report; and
  - (6) **Provide any additional comments that the CVA deems necessary.**