# §250.911. If my platform is subject to the Platform Verification Program, what must I do?


If your platform, conversion, or major modification or repair meets the criteria in [§ 250.910](/cfr/30/250.910.md), you must:

- (a) Design, fabricate, install, use, maintain and inspect your platform, conversion, or major modification or repair to your platform according to the requirements of this subpart, and the applicable documents listed in [§ 250.901(a)](/cfr/30/250.901.md?p=a) of this subpart;
- (b) Comply with all the requirements of the Platform Approval Program found in [§§ 250.904 through 250.908](/cfr/30/250.904..250.908.md) of this subpart.
- (c) Submit for the Regional Supervisor's approval three copies each of the design verification, fabrication verification, and installation verification plans required by [§ 250.912](/cfr/30/250.912.md);
- (d) Submit a complete schedule of all phases of design, fabrication, and installation for the Regional Supervisor's approval. You must include a project management timeline, Gantt Chart, that depicts when interim and final reports required by §§ [250.916](/cfr/30/250.916.md), [250.917](/cfr/30/250.917.md), and [250.918](/cfr/30/250.918.md) will be submitted to the Regional Supervisor for each phase. On the timeline, you must break-out the specific scopes of work that inherently stand alone (e.g., deck, mooring systems, tendon systems, riser systems, turret systems).
- (e) Include your nomination of a Certified Verification Agent (CVA) as a part of each verification plan required by [§ 250.912](/cfr/30/250.912.md);
- (f) Follow the additional requirements in [§§ 250.913 through 250.918](/cfr/30/250.913..250.918.md);
- (g) Obtain approval for modifications to approved plans and for major deviations from approved installation procedures from the Regional Supervisor; and
- (h) **Comply with applicable USCG regulations for floating OCS facilities.**

## Notes

### Authority

Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.

### Source

Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.