# §250.1753. After I decommission a pipeline, what information must I submit?


Within 30 days after you decommission a pipeline, you must submit a written report to the Regional Supervisor that includes the following:

- (a) A summary of the decommissioning operation including the date it was completed;
- (b) A description of any mitigation measures you took; and
- (c) A statement signed by your authorized representative that certifies that the pipeline was decommissioned according to the approved application.

## Notes

### Authority

Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.

### Source

Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.