# §203.90. What is in a fabricator's confirmation report?


This report shows you have committed in a timely way to the approved system for production. This report must include the following (or its equivalent for unconventionally acquired systems):

- (a) A copy of the contract(s) under which the fabrication yard is building the approved system for you;
- (b) A letter from the contractor building the system to the BSEE Regional Director for your region certifying when construction started on your system; and
- (c) Evidence of an appropriate down payment or equal action that you've started acquiring the approved system.