# §1000.1450. How are property and funding returned if there is a reassumption for substantial failure to carry out a construction project?


If there is a reassumption by the Secretary of a project for substantial failure to carry out the funding agreement or construction project agreement, property and funding will be returned as provided in subparts M and N of this part.


## Notes

### Authority

Authority: 25 U.S.C. 5373

### Source

Source: 89 FR 100245, Dec. 11, 2024, unless otherwise noted.