# §661.37. What are the funding limitations on an individual TTF bridge project?


The following funding provisions apply in administration of the TTFBP:

- (a) There are no funding limitations on an individual TTF bridge application, but the PE estimated cost will be based on the following fee scale:

  Estimated Construction Cost:

- (b) Requests for additional funds for PE or construction may be submitted along with proper justification to FHWA for consideration. The request will be considered on a case-by-case basis. There is no guarantee for the approval of the request for additional funds.

## Notes

### Authority

Authority: 23 U.S.C. 120(j) and (k), 202, and 315; 49 CFR 1.81, 1.84, 1.85; 23 CFR part 490, subpart D.

### Source

Source: 89 FR 57082, July 12, 2024, unless otherwise noted.