# §636.201. What selection procedures and award criteria may be used?


You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in [§ 636.202](/cfr/23/636.202.md)), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available:


## Notes

### Authority

Authority: Sec. 1503 of Pub. L. 109-59, 119 Stat. 1144; Sec. 1307 of Pub. L. 105-178, 112 Stat. 107; 23 U.S.C. 101, 109, 112, 113, 114, 115, 119, 128, and 315; 49 CFR 1.48(b).

### Source

Source: 67 FR 75926, Dec. 10, 2002, unless otherwise noted.