# §635.307. Coordination.

- (a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.
- (b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:
  - (1) [23 CFR part 140](/cfr/23/part140.md), [subpart I](/cfr/23/subpartI.md);
  - (2) [23 CFR part 646](/cfr/23/part646.md), [subpart B](/cfr/23/subpartB.md);
  - (3) [23 CFR 710.403](/cfr/23/710.403.md); and
  - (4) [23 CFR part 645](/cfr/23/part645.md), subpart A.

## Notes

### Amendments

[40 FR 17251, Apr. 18, 1975, as amended at 40 FR 25585, June 17, 1975; 64 FR 71289, Dec. 21, 1999]

### Source

Source: 40 FR 17251, Apr. 18, 1975, unless otherwise noted.

### Authority

Authority: Sections 1525 and 1303 of Pub. L. 112-141, Sec. 1503 of Pub. L. 109-59, 119 Stat. 1144; 23 U.S.C. 101 (note), 109, 112, 113, 114, 116, 119, 128, and 315; 31 U.S.C. 6505; 42 U.S.C. 3334, 4601 et seq.; Sec. 1041(a), Pub. L. 102-240, 105 Stat. 1914; 23 CFR 1.32; 49 CFR 1.85(a)(1).

### Amendments

[40 FR 17251, Apr. 18, 1975, as amended at 40 FR 25585, June 17, 1975; 64 FR 71289, Dec. 21, 1999]