# §140.605. Approval actions.

- (a) Authorization to proceed with preliminary engineering and acquisition of rights-of-way shall be issued in the same manner as for regularly financed Federal-aid projects.
- (b) Authorization of physical construction shall be given in the same manner as for regularly financed Federal-aid projects. The total cost and Federal funds required, including interest, shall be indicated in the plans, specifications, and estimates.
- (c) Projects subject to the reimbursable schedule shall be identified as an “E” project when the SHA is authorized to proceed with all or any phase of the work.
- (d) Concurrence in the award of contracts shall be given.

## Notes

### Source

Source: 48 FR 54971, Dec. 8, 1983, unless otherwise noted.

### Authority

Authority: 23 U.S.C. 101(e), 106, 109(e), 114(a), 120(g), 121, 122, 130, and 315; and 49 CFR 1.48(b).