# §4.71. Contents of application.


An application for license for transmission line only must contain the following information in the form specified.

- (a) **Initial statement.**
- (b) **Required exhibits.** The application must contain the following exhibits, as appropriate:
  - (1) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under [§ 4.41](/cfr/18/4.41.md);
  - (2) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 10 MW or less—Exhibits E, F, and G under [§ 4.61](/cfr/18/4.61.md); and
  - (3) For any transmission line that, at the time the application is filed, has been constructed and is proposed to be connected to any licensed water power project—Exhibits E, F, and G under [§ 4.61](/cfr/18/4.61.md) of this chapter.

## Notes

### Amendments

[Order 184, 46 FR 55942, Nov. 13, 1981, as amended by Order 413, 50 FR 11685, Mar. 25, 1985; Order 699, 72 FR 45324, Aug. 14, 2007; Order 877, 86 FR 42714, Aug. 5, 2021]

### Authority

Authority: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.

### Source

Source: Order 141, 12 FR 8485, Dec. 19, 1947, unless otherwise noted.