# §714.3. Advance declaration requirements for additionally planned production of Schedule 3 chemicals.

- (a) **Declaration requirements.**
  - (1) You must declare additionally planned production of Schedule 3 chemicals after the annual declaration on anticipated activities for the next calendar year has been delivered to BIS if:
    - (i) You plan that a previously undeclared plant on your plant site under [§ 714.1(a)(1)(ii)](/cfr/15/714.1.md?p=a-1-ii) of the CWCR will produce a Schedule 3 chemical above the declaration threshold;
    - (ii) You plan to produce at a plant declared under [§ 714.1(a)(1)(ii)](/cfr/15/714.1.md?p=a-1-ii) of the CWCR an additional Schedule 3 chemical above the declaration threshold;
    - (iii) You plan to increase the production of a Schedule 3 chemical by declared plants on your plant site from the amount exceeding the applicable declaration threshold to an amount exceeding the applicable inspection threshold (see [§ 716.1(b)(3)](/cfr/15/716.1.md?p=b-3) of the CWCR); or
    - (iv) You plan to increase the aggregate production of a Schedule 3 chemical at a declared plant site to an amount above the upper limit of the range previously declared under [§ 714.1(a)(1)(ii)](/cfr/15/714.1.md?p=a-1-ii) of the CWCR.
  - (2) If you must submit a declaration on additionally planned activities because you plan to engage in any of the activities listed in [paragraphs (a)(1)(i) through (iv)](#a-1-i..a-1-iv) of this section, you also should declare any changes to the anticipated purposes of production or product group codes. You do not have to submit a declaration on additionally planned activities if you are only changing your purposes of production or product group codes.
- (b) **Declaration forms to be used.** If you are required to declare additionally planned activities pursuant to [paragraph (a)](#a) of this section, you must complete the Certification Form and Forms 3-1, 3-2, and 3-3 as appropriate. Such forms are due to BIS at least 15 days in advance of the beginning of the additional or new activity.

## Notes

### Authority

Authority: 22 U.S.C. 6701 et seq.; E.O. 13128, 64 FR 36703, 3 CFR 1999 Comp., p. 199.

### Source

Source: 71 FR 24929, Apr. 27, 2006, unless otherwise noted.