# §305.8. Recipient-furnished equipment and materials.


The Recipient may wish to incorporate into the Project equipment or materials that it will secure through its own efforts, subject to the following requirements:

- (a) EDA must approve any use of Recipient-furnished equipment and materials. EDA may require that major equipment items be subject to a lien in favor of EDA and also may require a statement from the Recipient regarding expected useful life and salvage value of such equipment;
- (b) EDA may require the Recipient to establish that the expense claimed for such equipment or materials is competitive with current local market costs; and
- (c) Acquisition of Recipient-furnished equipment or materials under this section also is subject to the requirements of [2 CFR part 200](/cfr/2/part200.md).

## Notes

### Amendments

[71 FR 56675, Sept. 27, 2006, as amended at 79 FR 76132, Dec. 19, 2014; 82 FR 57054, Dec. 1, 2017]

### Authority

Authority: 42 U.S.C. 3211; 42 U.S.C. 3141; Department of Commerce Organization Order 10-4.

### Source

Source: 71 FR 56675, Sept. 27, 2006, unless otherwise noted.

### Amendments

[71 FR 56675, Sept. 27, 2006, as amended at 79 FR 76132, Dec. 19, 2014; 82 FR 57054, Dec. 1, 2017]