# §850.10. Development and approval of the CBDPP.

- (a) **Preparation and submission of initial CBDPP to DOE.**
  - (1) The responsible employer at a DOE facility must ensure that a CBDPP is prepared for the facility and submitted to the appropriate Head of DOE Field Element before beginning beryllium activities, but no later than April 6, 2000 of this part.
  - (2) If the CBDPP has separate sections addressing the activities of multiple contractors at the facility, the Head of DOE Field Element will designate a single DOE contractor to review and approve the sections prepared by other contractors, so that a single consolidated CBDPP for the facility is submitted to the Head of DOE Field Element for review and approval.
- (b) **DOE review and approval.** The appropriate Head of DOE Field Element must review and approve the CBDPP.
  - (1) The initial CBDPP and any updates are deemed approved 90 days after submission if they are not specifically approved or rejected by DOE earlier.
  - (2) The responsible employer must furnish a copy of the approved CBDPP, upon request, to the DOE Director, Office of Environment, Health, Safety and Security or designee, DOE program offices, and affected workers or their designated representatives.
- (c) **Update.** The responsible employer must submit an update of the CBDPP to the appropriate Head of DOE Field Element for review and approval whenever a significant change or significant addition to the CBDPP is made or a change in contractors occurs. The Head of DOE Field Element must review the CBDPP at least annually and, if necessary, require the responsible employer to update the CBDPP.
- (d) **Labor Organizations.** If a responsible employer employs or supervises beryllium-associated workers who are represented for collective bargaining by a labor organization, the responsible employer must:
  - (1) Give the labor organization timely notice of the development and implementation of the CBDPP and any updates thereto; and
  - (2) Upon timely request, bargain concerning implementation of this part, consistent with the Federal labor laws.

## Notes

### Amendments

[64 FR 68905, Dec. 8, 1999, as amended at 71 FR 68733, Nov. 28, 2006; 80 FR 5008, Jan. 30, 2015; 88 FR 41293, June 26, 2023]

### Authority

Authority: 42 U.S.C. 2201(i)(3), (p); 42 U.S.C. 2282c; 29 U.S.C. 668; 42 U.S.C. 7101 et seq.; 50 U.S.C. 2401 et seq., E.O. 12196, 3 CFR 1981 comp., at 145 as amended.

### Source

Source: 64 FR 68905, Dec. 8, 1999, unless otherwise noted.

### Amendments

[64 FR 68905, Dec. 8, 1999, as amended at 71 FR 68733, Nov. 28, 2006; 80 FR 5008, Jan. 30, 2015; 88 FR 41293, June 26, 2023]