# §707.17. Permissible actions in the event of contractor noncompliance.


Actions available to DOE in the event of contractor noncompliance with the provisions of this part or otherwise performing in a manner inconsistent with its approved program include, but are not limited to, suspension or debarment, contract termination, or reduction in fee in accordance with the contract terms.


## Notes

### Authority

Authority: 41 U.S.C. 8102 et seq.; 42 U.S.C. 2012, 2013, 2051, 2061, 2165, 2201b, 2201i, and 2201p; 42 U.S.C. 5814 and 5815; 42 U.S.C. 7151, 7251, 7254, and 7256; 50 U.S.C. 2401 et seq.

### Source

Source: 57 FR 32656, July 22, 1992, unless otherwise noted.