# §52.83. Finality of referenced NRC approvals; partial initial decision on site suitability.

- (a) If the application for a combined license under this subpart references an early site permit, design certification rule, standard design approval, or manufacturing license, the scope and nature of matters resolved for the application and any combined license issued are governed by the relevant provisions addressing finality, including §§ [52.39](/cfr/10/52.39.md), [52.63](/cfr/10/52.63.md), [52.98](/cfr/10/52.98.md), [52.145](/cfr/10/52.145.md), and [52.171](/cfr/10/52.171.md).
- (b) While a partial decision on site suitability is in effect under [10 CFR 2.627(b)(2)](/cfr/10/2.627.md?p=b-2), the scope and nature of matters resolved in the proceeding are governed by the finality provisions in [10 CFR 2.629](/cfr/10/2.629.md).

## Notes

### Amendments

[72 FR 49517, Aug. 28, 2007, as amended at 84 FR 63568, Nov. 18, 2019]

### Authority

Authority: Atomic Energy Act of 1954, secs. 103, 104, 147, 149, 161, 181, 182, 183, 185, 186, 189, 223, 234 (42 U.S.C. 2133, 2134, 2167, 2169, 2201, 2231, 2232, 2233, 2235, 2236, 2239, 2273, 2282); Energy Reorganization Act of 1974, secs. 201, 202, 206, 211 (42 U.S.C. 5841, 5842, 5846, 5851); 44 U.S.C. 3504 note.

### Source

Source: 72 FR 49517, Aug. 28, 2007, unless otherwise noted.

### Amendments

[72 FR 49517, Aug. 28, 2007, as amended at 84 FR 63568, Nov. 18, 2019]