# §420.33. Application requirements.

- (a) Consistent with [§ 420.32](/cfr/10/420.32.md) of this part, DOE shall set forth general and special project activity-specific requirements for applications for special projects financial assistance in the program guidance/solicitation.
- (b) In addition to any other requirements, all applications shall provide:
  - (1) A detailed description of the proposed project, including the objectives of the project in relationship to DOE's program and the State's plan for carrying it out;
  - (2) A detailed budget for the entire proposed period of support, with written justification sufficient to evaluate the itemized list of costs provided on the entire project; and
  - (3) **An implementation schedule for carrying out the project.**
- (c) DOE may, subsequent to receipt of an application, request additional budgetary information from a State when necessary for clarification or to make informed preaward determinations.
- (d) DOE may return an application which does not include all information and documentation required by this subpart, [10 CFR part 600](/cfr/10/part600.md), or the program guidance/solicitation, when the nature of the omission precludes review of the application.

## Notes

### Amendments

[61 FR 35895, July 8, 1996, as amended at 64 FR 46114, Aug. 24, 1999]

### Authority

Authority: Title III, part B, as amended, of the Energy Policy and Conservation Act (42 U.S.C. 6321 et seq. ); Department of Energy Organization Act (42 U.S.C. 7101 et seq. )

### Source

Source: 61 FR 35895, July 8, 1996, unless otherwise noted.